The Piper, Point Piper

External waterproofing works completed for a Class 2 multiresidential development comprising 14 luxury apartments, covering approximately 2,000m² of landscaped and external areas.

Client name:
Alliance Living
Location:
Wunulla Road, Point Piper NSW 2027
Project year:
Completed, 2025
Total value:
$170,000
No items found.

01. The Challenge

This project involved waterproofing over 2,200m² of balconies, rooftops, planter boxes, and landscaped podiums. The main challenge was heavily backfilled podium areas, demanding tailored systems and careful staging to ensure compliance with Australian Standards.

02. The Solution

Act Now applied liquid waterproofing to balconies, rooftops, landscaped podiums, and planter boxes, with cementitious systems in select zones. Over 2,200m² was treated to deliver a durable, compliant solution built for long-term performance. Works included:

  • Delivered a full external waterproofing package for a multi-residential development
  • Installed liquid-applied systems across balconies, rooftops, landscaped podiums, and planter boxes
  • Applied cementitious waterproofing to high-exposure zones requiring added durability
  • Successfully waterproofed 2,281m² of external areas
  • Ensured all works were compliant, durable, and designed for long-term performance

03. The Result

The project delivered over 2,200m² of compliant waterproofing across balconies, rooftops, podiums, and planter boxes, ensuring durable protection, long-term performance, and minimal disruption.